PKP Szybka Kolej Miejska
On 10 February 2021, the consortium of T4B and Maxto Technology entered into a contract with PKP Szybka Kolej Miejska w Trójmieście Sp. z o.o. for the construction of an integrated safety monitoring and information management system on railway line 250 together with the renovation of the building of the Suburban Railway Station in Gdynia and the SKM platform at the Gdynia Główna station.
The scope of the Project includes the preparation of design documentation and refurbishments of the platforms and track infrastructure.
The scope of the works includes the installation of information signs and CCTV cameras. The station is to be adapted to the needs of disabled persons.
The design also provides for the alteration of the historic suburban railway station in Gdynia without changing its unique character.
For the duration of the works, the passengers will be able to use a temporary facility.
The completion of the works is scheduled for the end of March 2023.
Project value: PLN 62,361,000.00 gross.
Update of the BVMS system at the Kraków Główny and Szczecin Główny railway stations
On 8/2/2021, the consortium of Maxto Technology and Maxto Sp. z o.o. S.K.A. entered into a contract with Polskie Koleje Państwowe Spółka Akcyjna for an update of the BVMS system at the Kraków Główny and Szczecin Główny railway stations and centralisation of the systems to the Railway Station Safety Centre in Warsaw together with the purchase of the required equipment.
Under the contract, the Contractor will update the BOSCH BVMS (Bosch Video Management Software) system at the Kraków Główny and Szczecin Główny railway stations to the latest version of the system complete with the delivery and replacement of the management server, arrays for the recorded materials, computer units, two operator stations and the delivery of 2 CCTV cameras.
The Contractor agreed to install, configure and test the installed equipment and software.
The value of the project was PLN 479,577.00 gross
General Directorate for National Roads and Motorways
On 19/11/2019, the consortium of Maxto Technology and Maxto S.K.A. entered into a contract with the General Directorate for National Roads and Motorways (GDKiA) for the construction of an emergency communication system at a section of the A1 and A4 motorways in Silesia Province.
The scope of the Project includes the following:
- surveying the existing telecommunication ducts in terms of their capacity and the possible use of the ducts to construct the emergency communication system
- preparing formal and design documentation and specifications of construction and testing requirements
- performing construction works
- providing maintenance services.
The value of the project is PLN 10,443,930.00 gross.